Do You Use SPC Correctly?

 

 

 

Misapplication of statistical process control can damage your operations


By Allise Wachs
President
Integral Concepts Inc.
West Bloomfield, MI


 


If a product fails or a process performs inadequately, we attempt to discover what's wrong so we can fix it. That sounds reasonable enough. By reacting to the problem, however, we're allowing that process or product failure to control our behavior. Isn't it more effective to understand and control the process rather than allowing the process to control us? 

 

 

                                                                                           

                                                                                                                                        

That's where Statistical Process Control (SPC) steps in. SPC is a set of techniques that provides a superior understanding about how a process behaves. In order to implement SPC, data must be collected over time.

When monitoring data, you expect variation--even when nothing out of the ordinary occurs. Common-cause sources of variation represent the inherent and natural level of variation affecting a process. But if data constantly fluctuate, how do you know whether something unusual has happened? SPC answers that question.

To understand whether the information varies in a predicted or unexpected way, you must understand the expected degree of system variation. Once you know the expected level of variability, you can identify whether your observations exceed the expected amount.

With SPC, the idea is to view a stable process long enough to understand the level of inherent variation. Using that information, you can compute limits of expected variation, otherwise known as control limits. To be valuable, these control limits must be computed and based upon data originating from a stable process.

When a statistic exceeds a control limit or unexpected patterns are observed, then you have evidence that a special-cause source of variation has entered the system. These special-cause sources of variation, otherwise known as assignable causes, result in unexpected changes in the process. This observation doesn't imply that the parts under production have exceeded specification limits--only that something unusual has entered the system.

Without SPC, these issues aren't visible until product measurements exceed specification limits--if they are found at all. Unfortunately, by then it's too late. Bad products have already been produced. The company has invested time and resources producing an inferior product, further eroding profitability. Moreover, discovering the root causes is more difficult at that point.

SPC not only provides the opportunity to identify unusual behavior before unacceptable products are produced, it allows you to determine when something unexpected occurred. Sadly, most companies don't take advantage of SPC's benefits.

Many manufacturers don't require evidence of process stability from their suppliers (or sometimes from themselves). Without that information, we not only discover the problem too late, but it's more difficult to determine the cause.

We have seen American automotive companies spend much more time and money dealing with warranty issues than several of their Japanese counterparts. The inability to effectively reduce variation and a lack of responsibility in ensuring dimensional stability has much to do with it.

When the process distribution changes, no one, including the manufacturer and customer, knows what to expect. That's not to say that every change is bad. Some unexpected changes might represent an improvement, but unless we appreciate that an improvement was made, we won't sustain that progress.

Of course, many people who work in a manufacturing environment still don't believe that processes change. They're wrong. Processes can change due to a variety of factors including changes in supplied parts, temperature, humidity, worn tools, or changes in personnel.

We routinely use X-bar and R charts to monitor change. The X-bar chart helps to detect changes in the process average, while the R chart is designed to determine changes in process variability. When properly used, these charts can be effective indicators of process behavior, as well as a tool to predict quality improvement or decline.

Unfortunately, most American manufacturers don't use these charts correctly.

To understand why, let's look at the mechanics behind the X-bar chart. It's commonly written as an X with a bar over it--a symbol that denotes an average or mean.

Typically, a production operator will take a few measurements over a period of time. The operator averages those measurements and places the results on an X-bar chart. Then the range--the maximum data point minus the minimum data point--is computed and placed on the R chart.

Control limits are computed. These describe the expected amount of variation among the averages (on the X-bar chart) and ranges (on the R chart) as long as the process remains in control. By design, control limits should capture about 99.7% of the dots on the chart when the process is stable.

While some quality professionals believe that control charts indicate the ability to meet specifications (process capability), that's completely untrue. Control charts were invented to serve one purpose--to identify process changes as quickly as possible after the change occurs. They do nothing more and nothing less.



This graphic uses an X to illustrate the individual measurements for a few of the averages. The six individual measurements that create the average are widely scattered. Averages always possess less variation than individual measurements.
 

So why look at averages if they are so misleading that they can't indicate whether parts conform to specification limits? There are two compelling reasons to do so.

First, and most importantly, averages detect process shifts more quickly than individual measurements--which is the reason for implementing SPC. (This assumes the appropriate sample size has been determined.) Second, averages from a stable process tend to follow a normal distribution, so it's easy to estimate control limits for averages. Contrary to popular belief, individual measurements typically do not follow a normal distribution--even when a process is stable.

Specification limits do not belong on control charts. Processes that are in control do not necessarily produce parts within specification. Moreover, production of "acceptable" parts doesn't imply that processes are stable.

There are numerous fundamental errors typically made in applying SPC, and this article has touched on only a few. All the mistakes result in misjudging reality.

Additional common mistakes include improper sampling methods. The method employed to take physical samples is critical. Furthermore, the type of control chart used depends on the type of sampling scheme used. There are instances where rational sampling (I'll explain) is required and instances where we can violate that method as long as appropriate SPC methods accompany the sampling plan.

A rational sample is a group of measurements that come from a single distribution. An example of a violation of rational sampling might be measurements taken from several cavities from an injection molding machine, when at least one cavity differs from the rest. The measurements then do not come from one distribution. There are efficient techniques available to handle situations where rational samples aren't possible, but traditional X-bar and R charts are not effective.

Inappropriate sample sizes are nearly always used. While a sample size of five may determine some process changes, it will not determine others very quickly. The most appropriate sample size depends on the application and the amount of change deemed critical to detect. The consequence of using inappropriate sample sizes in SPC include the inability to detect important process shifts. While a sample size (subgroup size) of three detects large shifts, a sample size of more than three is necessary to detect smaller shifts quickly.



These are sample X-bar and R charts. The average of averages and the average range are solid bold lines, while control limits (UCL, LCL) are indicated by dashed lines. The top graph shows that averages are expected to randomly fluctuate between 77.7 and 82.3 about 99.7% of the time. When the process is stable, ranges should randomly fluctuate between 0 and 8.5.
 

Individual measurements should only be used for control charting in certain situations, and when using individual measurements, several issues such as the chart's ability to detect important changes must be evaluated. Often, charts such as Cumulative Sum (CUSUM) and Exponentially Weighted Moving Averages (EWMA) are effective on individual measurements because they don't depend heavily on the distribution of individuals, and they can be designed with varying degrees of sensitivity to detect important changes. CUSUM and EWMA charts are most valuable when the sample size is restricted to one or two. Due to an inadequate sample size, important shifts cannot be detected with traditional X-bar and R charts. But CUSUM and EWMA charts transform the individual readings so that the required process shifts are detected.



Taking measurements over time helps manufacturers better understand whether their processes are stable or in control. But what exactly does that mean? Company ABC produces spring clips. Knowing that the radius of a spring clip is an important dimension, the manufacturer measures the radius of spring clips produced over a few minutes. If the radius data were collected on another day, you shouldn't expect to see the identical radius values. But the distribution of the data should remain nearly the same. When you spot the same distribution repeatedly over time, the process is said to be in control. The radius data above represent distribution #1. When monitoring the process at future points in time, the same distribution pattern emerges. This process is stable or "in control." It's risky to assume that these radius dimensions will always follow the same distribution. Numerous factors such as material properties, machine settings, and environmental conditions will affect dimensions. But many manufacturers believe that being in control isn't important as long as the product meets its specification limits. That belief has negative consequences for American businesses striving to achieve quality and efficiency.
 


Here's what happens when a product characteristic meets specifications, but isn't in control. The top graph represents a product that meets both Upper Specification Limit (USL) and Lower Specification Limit (LSL) but is not stable. Once customers receive units that follow a particular distribution, they expect to see the same distribution again. Customers like consistency. If they suddenly receive a different distribution, they are usually disappointed with the perceived lack of quality. At least, they do not expect the change. The problem becomes magnified if these distributions represent an important dimension for pieces that will be mated together. Units from one distribution will fit together differently than units from a different distribution, so you can't expect products to perform consistently. The varying performance means less-predictable failure times and less-predictable customer responses. Compare distribution #3 to distribution #2. Which do you think customers would prefer? Knowing they prefer consistency, #3 is the clear choice, even though both depict products that fall within specification limits.
 

In many applications, variation should be decomposed so that we understand the variation within a sample (range within charts) and the variation between samples (range between charts). Essentially, there are at least two significantly different sources of variation in the system. Many common production methods introduce multiple sources of variation, and traditional X-bar and R charts are misleading in these cases.



Examine this X-bar chart. Both the control and specification limits are shown. If the process remains stable, would you expect that the characteristic being plotted will be within the specification limits most of the time? Many would say yes, but this is an erroneous conclusion, and the consequences may be severe. Remember, you're not looking at individual measurements being plotted on the chart. You are looking at averages. Control limits suggest that if the process is stable the averages will remain within those limits 99.7% of the time. But don't forget that specification limits apply to individual measurements--not averages.
 

Many applications require standardized charts that account for differences in sample sizes or different weighting schemes.

The use of capability indices such as Cp, Cpk, Pp, and Ppk is almost always misleading. For one thing, analysts try to assess process capability without ever establishing process stability first. Next, many data analysts assume the data follow a normal distribution when it usually does not, so gross errors in estimates are made unless the non-normal data are properly analyzed. Simple and superior methods for assessing capability are available, yet they are rarely used. For example, focusing on the actual data distribution, its standard deviation, its median, and the proportion of parts exceeding specification limits would serve us much better.

These mistakes are serious in the sense that they result in erroneous conclusions, manufacturing problems, premature product failures, dissatisfied customers, high warranty costs, and even product liability suits.

Proper application of SPC aids in our understanding of system variation and indicates when that variation increases or decreases. This knowledge puts you--not your system--in control.


This article was first published in the March 2005 edition of Manufacturing Engineering magazine.


Published Date : 3/1/2005

Advanced Manufacturing Media - SME
U.S. Office  |  One SME Drive, Dearborn, MI 48128  |  Customer Care: 800.733.4763  |  313.425.3000
Canadian Office  |  7100 Woodbine Avenue, Suite 312, Markham, ON, L3R 5J2  888.322.7333
Tooling U  |   3615 Superior Avenue East, Building 44, 6th Floor, Cleveland, OH 44114  |  866.706.8665